Estimate the production in loose cubic meter per hour for a medium- weight clamshell excavating loose earth, Heaped bucket capacity is 0.9 m3, The soil is common earth with a bucket fill factor of 0.95,Estimated cycle time is 50 s and Job efficiency is estimated at 50 min/h. Select one: O a. 51.3 b. 57 C. All choices are incorrect O d. 53 e. 85.5
Clamshell Production Example • Estimate the production in loose cubic yards per hour and in loose cubic meters per hour for a medium-weight clamshell excavating loose earth. • Heaped bucket capacity is 1.0 cy, [0.75 m 3 ]. • The soil is common earth with a bucket fill factor of 0.95. • Estimated cycle time is 40 s.
[Find the expected production in loose cubic yards (LCM) per hour Of a small hydraulic excavator. Heaped bucket capacity is % cu yd (0.57 m y). The material is sand and gravel With a bucket fill factor Of 0.95. Job efficiency is 50 min/h. Average depth Of Cut is 14 ft (4.3 m). Maximum depth Of cut is 20 ft (6. I m) and average swing is 90.
11. Find the expected production in loose cubic meter (LCM) per hour of a 2.3-m3 hydraulic shovel equipped with a front-dump bucket. The material is common earth with a bucket fill factor of 1.0. The average angle of swing is 75&سؤال
The total hydrogen production capacity of the project is 4000 standard cubic meters per hour, with a rated hydrogen production capacity of 2000 standard cubic meters per hour in the first phase. It can produce 4200 kilograms of 99.999% pure hydrogen per day. According to the preliminary calculation of the world's first renewable energy hydrogen
[Clamshell Production Example • Estimate the production in loose cubic yards per hour and in loose cubic meters per hour for a medium-weight clamshell excavating loose earth. • Heaped bucket capacity is 1.0 cy, [0.75 m 3 ]. • The soil is common earth with a bucket fill factor of 0.95. • Estimated cycle time is 40 s.
[Study with Quizlet and memorize flashcards containing terms like Find the swell and shrinkage of a soil weighs 1661 kg/m3 in its natural state, 1186 kg/m3 after excavation and 2077 kg/m3 after compaction., A soil weighs 1163 kg/Lm3, 1661 kg/Bm3 and 2077 kg/Cm3. How many bank cubic meter (Bm3) and compacted cubic meter (Cm3) are contained in 593,300 Lm3 of this soil?
[Find the expected production in loose cubic meters per hour of a 23 m3 hydraulic shovel equipped with a front -dump bucket The material is common earth with a bucket fill factor of 10 The average angle of swing is 75 degrees and job efficiency is 08 CYCLES OUTPUT 150 cycles/h Swing 105 HINT PRODUCT (LCM/h) = CxSxVxBxE A 200 LCM/h B 290 LCM/h C 299 LCM/h D 209 LCM/h
[All values are in meters., Find the volume of excavation required for the area shown in Figure 4. The figure at each grid intersection represents the depth of cut at that location. Depths in parentheses represent meters., Find the expected production in loose cubic meters (LCM) per hour of a small hydraulic excavator.
[EXCAVATING MACHINES HYDRAULIC EXCAVATORS Hydraulic excavators are hydraulically powered machines with a backhoe of front end. Hydraulic excavators have a number of advantages over cable controlled excavators including: - Faster cycle time - Higher bucket operations force - More precise digging - Easier operator control In addition to backhoe and
[Find the expected production in loose cubic yards per hour of a medium hydraulic excavator. Heaped bucket capacity is 2.0 cu yd. The material is sand. Job efficiency is 45 min / h.Average depth of cut is 16 ft.Maximum depth of cut is 32 ft and average swing is 18 0 ∘ For Question 2, determine the expected production in compacted cubic yards per hour if the shrinkage factor is
[B) find the expected production in loose cubic meter per hour of a small hudraulic excavtor. Heaped bucket is 0.57 m3. The material is sand and gravel with a bucket fill of 0.95, job effciency of 50 min/hour . average cut of 4.3m and maximum depth of cut of 6.1 m and average swing of 91 deg. d) Explain the term “ Estimates” in the context of
[(APR 2024, NOV 2023, MAY 2022, NOV 2021) Find the expected production in loose cubic yards (LCM) per hour of a small hydraulic excavator. Heaped bucket capacity is 3⁄4 cu yd (0.57 m3). The material is sand and gravel with a bucket fill factor of 0.95. Job efficiency is 50 min/h.
[Answer to Determine the expected dragline production in loose. Engineering; Civil Engineering; Civil Engineering questions and answers; Determine the expected dragline production in loose cubic meters (LCM) per hour based on the following information: Dragline size = 2 m3 Swing angle = 100&سؤال
The loader has a bucket capacity of 2.5 cubic yards. The soil has a fill factor of 1.2 and a weight of 2,500 lbs per LCY. The loader has an STL of 50% of 15,000 lbs. The loader will haul in one direction loaded at 2.5 miles per hour and return at 3.5 miles per hour. The total cost of the tractor is $55.00 per hour. It has a fixed time of .35
[Engineering; Civil Engineering; Civil Engineering questions and answers; Find the expected production in loose cubic yards per hour... medium hydraulic excavator heaped bucket capacity is 0.80 LCY sand and gravel bucket fill factor is 0.93 job efficiency is 50 min/hr average depth of cut is 16 ft maximum depth of cut is 22ft average swing is 45 degrees
[1 Barrel of Water per Day: Daily production rate of barrels of water. Standard industry petroleum barrel being used, exactly 42 gallons (U.S. fluid measure). 1 Cubic Meter per Hour: Volume flow rate of 1 cubic meter per hour. A flow of 1 cubic meters per 3600 seconds (SI units). 1 m 3 /h ≈ 0.000 277 777 7778 m 3 /s. Link to Your Exact
[Free online flow converter - converts between 58 units of flow, including cubic meter/second [m^3/s], cubic meter/day [m^3/d], cubic meter/hour [m^3/h], cubic meter/minute, etc. Also, explore many other unit converters or learn more about flow unit conversions.
[Instant free online tool for cubic meter to gallon (US) conversion or vice versa. The cubic meter [m^3] to gallon (US) [gal (US)] conversion table and conversion steps are also listed. Also, explore tools to convert cubic meter or gallon (US) to other volume units or
[a. Calculate the price of pit-run gravel delivered to the site per cubic yard (bank measure) based on the following data: ∙ The pit is located 10 miles from the site. ∙ Trucks cost $ 43.75 per hour, including fuel and maintenance; they have 12 cubic yards (loose material) capacity and travel at an average speed of 30 miles per hour. ∙ The swell factor for this material is 15 %. ∙
[Question: c. Find the expected production in loose cubic meters (Lm3) per hour of a 2.3 m3 hydraulic shovel equipped with a front-dump bucket. The material is common earth with a bucket fill factor of 1.0. The average angle of swing is 90∘ and job efficiency is 0.85 . (4)
[Find the expected production in loose cubic yards (LCM) per hour of a small hydraulic excavator. Heaped bucket capacity is 3⁄4 cu yd (0.57 m3). The material is sand and gravel with a bucket fill factor of 0.95. Job efficiency is 50 min/h. Average depth of cut is 14 ft (4.3 m).
[